Plant Information : TKPS - 330 MW Combined Cycle Power Plant


Plant Capacity 2 X 110 MW Gas Turbines
1 X 110 MW Steam Turbine
 
Gas Turbine Manufacturer General Electric
 
Gas Turbine Model Frame 9E (MS 9001E)
 
Steam Turbine Manufacturer General Electric
 
Steam Turbine Model SC4
 

HRSG Manufacturer

Despatch Mode

Nooter / Eriksen

Fully despatchable base-load

 
Management System

MS ISO 9001:2000
(Quality)

MS ISO 14001:2004
(Environmental)

OHSAS 18001:2007
(Occupational Health & Safety)

Milestones
21st January 2002
Financial Close
 
6th August 2000 Commencement of Power Purchase Agreement Tenure
 
5th August 2000 End of Stabilisation Period
 
6th August 1999 Takeover of TKPS
 
6th August 1999
Completion of Asset Sale Agreement
 
2nd February 1999
Execution of Power Purchase Agreement
 
2nd February 1999 Execution of Asset Sale Agreement